Ohio and Pennsylvania Explore Surplus Interconnection Service to Accelerate Grid Capacity and Reduce Costs
U.S. electricity demand has been steadily climbing for the past five years, creating an urgent need for new energy resources. However, complex review processes for connecting these resources have delayed over 2,060 gigawatts of generation and storage capacity nationwide. In Ohio and Pennsylvania, new energy resources typically take more than five years to become operational, leading to surging generation costs. Two new studies, funded by Pew Charitable Trusts, suggest that 'surplus interconnection service' (SIS) could offer a solution. SIS allows new energy resources, such as solar farms or utility-scale batteries, to connect to the grid by utilizing the unused capacity of existing power plants. This mechanism leverages the fact that many power plants operate below their maximum potential for significant portions of the year, effectively allowing new resources to 'piggyback' on existing grid connections.