Passengers travelling through New Delhi Railway Station may soon need to check their boarding stations carefully as Indian Railways prepares a large-scale
train shifting exercise linked to the station’s mega redevelopment project. The redevelopment work, expected to continue till around 2030, aims to develop NDLS into an airport-style multi-modal transport hub with higher passenger capacity, underground subways, expanded parking and modern waiting areas. To reduce crowding and inconvenience during construction, several trains are likely to be shifted to stations including Anand Vihar Terminal, Hazrat Nizamuddin Railway Station, Shakur Basti Railway Station, and Delhi Safdarjung Railway Station. Also Read | New Delhi Railway Station To Be 'Super Smart' - AI Cameras, New Buildings, Faster Entry And More Around 30 trains are expected to be shifted in the next two months, while nearly 100 trains may eventually operate from alternate stations during the phased redevelopment work.
Which Trains Are Likely To Shift?
| Train Name | Likely New Station | Route Direction |
| New Delhi–Rani Kamlapati Bhopal Shatabdi | Hazrat Nizamuddin | Madhya Pradesh |
| Taj Express | Hazrat Nizamuddin | Agra |
| Dr Ambedkar Nagar Superfast Express | Hazrat Nizamuddin | Madhya Pradesh |
| Dehradun Shatabdi Express | Anand Vihar | Uttarakhand |
| Kathgodam Shatabdi Express | Anand Vihar | Uttarakhand |
| Prayagraj Humsafar Express | Anand Vihar | Uttar Pradesh |
| Purva Express | Delhi Safdarjung/Shakur Basti | Howrah |
| Vaishali Express | Delhi Safdarjung/Shakur Basti | Saharsa via Barauni |
| Some Varanasi-bound trains | Shakur Basti | Uttar Pradesh |
| Maharashtra and Gujarat-bound trains | Shakur Basti | Western routes |
| Special Barauni and Darbhanga trains | Delhi Safdarjung | Bihar |
Three-Phase Redevelopment Plan At NDLS
The redevelopment work has already started near Platform Number 1 at New Delhi Railway Station. The modernisation project is expected to take three to four years and will be completed in phases:| Phase | Platforms Covered |
| Phase 1 | Platforms 1 to 5 |
| Phase 2 | Platforms 6 to 10 |
| Phase 3 | Platforms 11 to 16 |