New Delhi, Dec 19 (PTI) Shree Cement, the country's third largest cement maker, on Friday said it has declared a lockout of a cement plant at Baloda Bazar in Chhattisgarh's Raipur from December 18.
This
is "due to non-co-operation of workmen," Shree Cement said in a regulatory filing.
On the estimated impact on the production/operations, the Kolkata-based company said, "Based on current operations, there will be an estimated loss of cement production of around 10,000 tonne per day."
The company is monitoring the situation and will provide update on further developments in due course, it added.
"The company is in the process of ascertaining the loss caused by the lockout," it said.
Shree Cement has a clinker grinding unit with a 3.4 million tonnes per annum capacity, which was commissioned on April 20, 2025.
It has an installed cement production capacity of 50.4 MTPA and power generation capacity of 742 mega watts, including renewable energy sources. PTI KRH TRB