Ahmedabad, Nov 21 (PTI) The Overhead Equipment (OHE) system on Surat-Bilimora section of the Mumbai-Ahmedabad bullet train corridor has been successfully energised, the NHSRCL said on Saturday, terming it a significant milestone.
The OHE system was energised on November 20 as per the schedule, it said in a release here.
The 50-km long section includes both Up and Down lines and marks important progress towards further testing for the project, said the National High Speed Rail Corporation Limited (NHSRCL), the implementing agency.
Energisation will be carried out progressively in smaller sections to ensure safety and compliance with prescribed procedures, it said.
The bullet train corridor is equipped with an advanced 2×25 kV Overhead Traction System,
one of the sophisticated electrification technologies used for high-speed rail systems worldwide, the NHSRCL said.
“The electrification network comprises 14 strategically located Traction Substations (TSS) along the 508-km corridor. These substations will receive power from the National grid and supply it to the overhead traction system,” the release said.
The first traction substation at Bilimora, in Navsari district of Gujarat, has completed installation works in the Control Panel, Changeover Switch, Transformer and Circuit Breaker buildings.
The TSS in Gujarat will receive power from the 220 kV Ambetha Grid Substation of Gujarat Energy Transmission Corporation Limited (GETCO).
The elevated alignment between the two stations includes bridges across four rivers and a steel bridge over National Highway 53. The viaduct is also equipped with some 94,000 noise barriers to minimise noise impact, the release said.
The NHSRCL also advised the public to not approach or touch overhead electrical installations or undertake any unauthorised work near them.
The bullet train corridor has stations planned at Mumbai, Thane, Virar, Boisar, Vapi, Bilimora, Surat, Bharuch, Vadodara, Anand/Nadiad, Ahmedabad and Sabarmati.
The government is aiming to launch the first phase of the project by around mid-2027, between Surat and Vapi in Gujarat. PTI KA KRK