Silver Storm Mining Ltd. has commenced rehabilitation activities at its La Parrilla Silver Mine Complex in Durango State, Mexico. The company has engaged Dynamic Engineering Services Ltd. to oversee the
rehabilitation of the processing plant, which includes expanding the sulphide circuit to 1,250 tonnes per day. This expansion represents a 25% increase in capacity, aligning with the mineralization profile of La Parrilla. The rehabilitation process involves drift cleaning, scaling, ventilation upgrades, and recommissioning of underground services. The company aims to complete these activities within seven to nine months, potentially restarting operations by the second quarter of 2026. SRK Consulting (Canada) Inc. has been engaged to review the restart plan, focusing on geomechanical, ventilation, water management, and mineral processing considerations.
Why It's Important?
The rehabilitation of La Parrilla Silver Mine is significant for Silver Storm Mining Ltd. as it marks a strategic move towards resuming production and generating value for shareholders. The expansion of the sulphide circuit is crucial for optimizing the processing of the mine's mineral resources, which could enhance the company's output and profitability. This development is also important for the local economy in Durango, Mexico, as it could lead to job creation and economic growth in the region. However, the absence of a preliminary economic assessment or feasibility study introduces risks, as the project relies on internal data and historical reports, increasing the uncertainty of economic and technical viability.
What's Next?
Silver Storm plans to continue with the rehabilitation activities, aiming for completion within the next seven to nine months. The company has ordered new equipment, including flotation cells and a cyclone, expected to be delivered by December 2025. Following the mechanical completion, Dynamic Engineering will manage the commissioning activities. The potential restart of operations is targeted for the second quarter of 2026, contingent on further technical evaluations. Stakeholders, including investors and local communities, will be closely monitoring the progress and outcomes of these rehabilitation efforts.
Beyond the Headlines
The rehabilitation of La Parrilla Silver Mine could have broader implications for the mining industry in Mexico, potentially setting a precedent for other companies looking to restart operations at historic sites. The project highlights the importance of strategic planning and technical evaluations in ensuring the economic viability of mining operations. Additionally, the involvement of SRK Consulting underscores the need for expert reviews in mitigating risks associated with such projects.